03-28-2024  10:11 am   •   PDX and SEA Weather
City of Portland Environmental Services
Published: 12 May 2017

Environmental Services continues a project to repair or replace 17,000 feet (more than 3 miles) of public sewer pipes in the Humboldt neighborhood that are on average 85 years old and in deteriorating condition. This project will protect public health and our environment by reducing the possibility of sewage releases to homes, businesses and streets.

CONSTRUCTION SCHEDULE

The map posted at www.portlandoregon.gov/bes/humboldt shows the anticipated construction locations through May 26. Please be aware that schedules are subject to change due to a variety of factors, including conditions underground, weather, traffic impacts and subcontractor and materials availability.

Residents and businesses should expect periods of inactivity between each phase ranging from a few days to a few weeks. The duration depends on a variety of variables including underground conditions, weather, traffic impacts, subcontractor schedules, quality control tests and availability of materials. To learn more about What to Expect During Construction go to www.portlandoregon.gov/bes/article/632833.

FOR MORE INFORMATION

Visit the project web page at www.portlandoregon.gov/bes/humboldt

or contact Matt Gough at 503-823-5352 or matthew.gough@portlandoregon.gov.  

Thank you for your cooperation during this project. Please let us know if you have questions or concerns such as effects on business operations, medical or business deliveries, the need for help with access for people with disabilities, or other concerns. We appreciate your communication and want to hear from you. 

Recently Published by The Skanner News

  • Default
  • Title
  • Date
  • Random

The Skanner Foundation's 38th Annual MLK Breakfast